Ever wondered what it takes to run and build a campsite?
Here's a glimpse into the past 12 months. We keep a log of the main things happening to do with camp - it doesn't include everything but is a great reminder of the work we've done over the year! A lot of it is spent in front of computer for our Exec Team!
1st April - 26th April
-
1st - Ste planted 6 oaks and Green beech
-
2nd - Mike and Ste cut large field and strimmed round trees
-
3rd - Matt and Dan borrowed barrel at lunch, Mike and Ste cut large field and strimmed round trees
27th April - 26th May
-
Begun to remove pines to accommodate re-siting of containers
-
Begun to spray main field to remove grass
-
Took small Kubota to be looked at by Birchalls - verdict? Broken beyond repair
-
Large Kubota bearing issues?
-
All areas of grass now under control
-
Padlock on New Barrier damaged (2nd time in a month)
-
Mike, Ste and Dasa created new site
27th May - 30th June
-
Large tractor maintenance, coolant, grease and oil
-
Push mowers serviced (oil)
-
Mike set up online forms / payment emails to Sarah
-
Business rate rebate email sent to David Harvey - thanks Haydn!
-
Mike received SCC email - £1,000 rebate - Ste authorised and is now in bank account
-
Audit and tidy up of all existing fuel and oil. Removal of old liquids
-
Confirmed attendance for all staff members agreeing to follow new Covid-19 guidance
-
Draft lawnmower options drawn up
-
Begun tidy up of pines area ready for Josh to come and begin removal of soil etc.
-
New campsite regulations received from Mike
-
£510 paid to Peel L&P for rent owed
-
Promoted Standing Order donations for Hollinwood (Hollinwood Heroes)
30th June - 28th July​
-
Another invoice from Peel - check with Treasurer what's happening
-
Sent Camp Report to County covering April 1st 2019 - March 31st 2020
-
Contacted new communications team
-
Email from Group re large work party weekend in Sept??
-
Contacted by a new member who is coming down on July 18th​
-
Accepted offer of spare double sink
-
£191.00 of donations since 26th June - unsure as yet as to whether these will be ongoing
-
Paid a further £400+ to Peel Land and Property
-
Mike and Ste meeting with Haydn Worrall to discuss reopening
29th July - 1st September
-
New bridge built
-
Contacted Salford Rangers who gave Ste an email address
-
Met Rob onsite with GPS. Datum points are 20 metres out... Ste and Mike to contact Architect
-
Online meeting with camp managers
-
Next day GM on Red alert and therefore no f2f scouting…
-
Lock removed from barrier. Ste contacted Peel
-
Peel to replace with combi lock but no word as of 21.8.21
-
-
Contacted Work Party group to rearrange work party weekend to Spring 2021
-
Emailed (RHS) to request items from building works
-
Emailed High Sheriff's fund (GMP) to see about large grant request
-
Application submitted 21.8.20
-
Application for £3,500 - need to fund a further £3,965 to meet quote price
-
Approval meeting is happening in November
-
-
Emailed RHS about GGB
-
Received reply. Reconnect in early 2021. Like idea of Living Willow structure
-
-
Missing tools
-
Spoke to ex-MEN journalist re story about Hollinwood
2nd September - 29th Sept
-
Applying for Selco grant
-
Jobs for autumn now on the board - is there a better way of getting input from team? Committee meetings?
-
Final grass cutting taking place this month
-
Oak trees delivered. Who from?!
-
Salford grass cuttin contact cancelled due to illness
-
Exec member has been in touch to say that Peel are wanting to meet. Arranging asap
-
Ste and Mike met with Peel and Contractor on 24.09.20
-
Peel are going to clear the ditch around the west perimeter
-
And have begun to cut back the grass etc. They will remove small trees to enable fence
-
Maintenance is then up to us
-
M and M are available to hire in the future
-
Elecs coming from Neighbouring farm
-
Water coming via conduit over Moorings bridge probably
-
Topo guys will peg out the car park (smaller than originally planned but keeps the nice paths etc as agreed with Mike and Ste - losing grass median)
-
Peel happy with putting containers in area that we think is necessary
-
Topo guys also pegging out boundaries at canal side??
-
Car Park to be finished by Nov. £10 per tonne and there is already 3,000 tonnes down!?!
-
Will put in a pipe - supplied by us - to future proof car park
-
Mike has priced up 60m of twin wall pipe £294.18 - paid for by Hollinwood Hero donations
-
-
Edge of car park will be 3 or 4 feet from line of stakes currently in place
-
-
Scouting exempt from government guidance and as such is on AMBER level - 25th Sept
-
See meetings and associated actions with other campsites
-
Other than risk assessments what else do we need to do to 'open'
-
Tape of construction areas plus other
-
QR posters downloaded and printed
-
30th Sept - 2nd Nov
-
Ste, and other exec team met with Peel 12th October
-
To agree date of pegging out of car park
-
And agreed to share monthly updates from now on (See Peel email)
-
-
10 harras fencing panels from Team
-
Bonfire cancelled
-
Ste and Mike have been absent for a few weeks. Ste with holiday, quarantine and house renovations, Mike with holiday and quarantine. Sorry about this, will be back soon
-
Cycle shelter roofing is progressing
-
GM in tier 3 - hasn't affected Scouting since the last update
-
However, please be aware that we must keep to current guidelines i.e. no more than 6 people meeting on site
-
-
GMP using the site more regularly - please keep this in mind
-
Awarded GMP grant. Cheque in post (£3,500)
-
Unity Insurance forms completed and sent
3rd Nov - 23rd Nov
-
Crew
-
Lockdown has meant we have had to suspend staff visits until Dec 2nd at the earliest (apart from security checks)
-
-
Car Park has started!
-
Contractor is filling in car park footprint
-
Drainage pipe ordered, paid for (Mike), and delivered onto site (Thanks Matt M for collecting)
-
As well as lighting ducting
-
Contractor has plans and will install
-
-
Fundraising
-
£3.5k cheque (GMP) paid in by Treasurer
-
-
Website and Newsletter
-
Bought plan to create website @ £4.00 per month up until 17.11.2022
-
Ste to put expenses claim in for 1-off payment for website
-
Now need to build, edit, promote the website
-
-
Surveying
-
Boundary markers now finalised with metal stakes in place. Please do not remove!
-
Measured out full extent of compound area
-
Including marking out western corners of Wardens' and Phase 1 building.
-
Middle culvert likely to be the back entrance to compound
-
Need to clear, tidy, level, begin hedging off this area asap
-
-
-
Next Peel update on 25th November but….
-
CARBON FOOTPRINT – looking for places to plant trees. One idea is for the fence alongside the ditch. Carbon footprint, 3,000 trees 6 trees per metre. Native species 1 and 2 year old
-
-
RHS - Greening Great Britain
-
Other useful things to send through ASAP would be (mandatory for GGB groups):
-
Evidence of landowners permission
-
A copy of your current Public liability insurance if relevant
-
-
25th Nov - 2nd Feb 2021
-
Peel update received. Need to share before meeting OR go through during meeting
-
Exec committee have decided to decline the offer of the 3,000 trees from Peel
-
Friday 27th Nov
-
Deer-gate
-
2x public announcements from Peel about culling 10 Roe deer in fenced-off area of RHS site (Middlewood)
-
Almost 2k comments on social media
-
Petition set up with over 5k signatures within 3 days
-
Councillors signed letters denouncing actions
-
Robin Garrido on BBC / ITV reports
-
Hollinwood post about relocating deer seen by over 14,000 people
-
Shared by Barbara Keeley
-
Emailed all the ward councillors, Paul Dennet, Barbara Keeley and Richard Green
-
Replies from BK and KG and Richard Green
-
-
Spoke with RHS who are meeting Ste and Mike after Christmas
-
-
Spoke to Environment Agency to report incident of flooding
-
See email from 5th Jan 2020 for response
-
Next steps are:
-
Board of arbitration
-
Have contacted contractor about a quote to clear pond area
-
-
-
Spoke to RHS
-
Requested that we push GGB grant back to autumn 2021
-
Unclear at this stage how we build a living willow structure for £500
-
Advised RHS that Hollinwood would NOT be able to find extra money to complement
-
Think of other ideas in the meantime
-
-
Exec shared £1,000 Unity prize on Crew Page - No update as far as we know (Feb 2021)
-
Met with RHS Bridgewater at Middlewood
-
Agreed to offer on long-term loan the Mosaic (currently in storage)
-
-
Met RHS at Hollinwood
-
Discussed potential of Hollinwood
-
And also the relocation of Roe Deer at the wood
-
-
I-Beam from Team member (many thanks!)
-
Spoke with Charity-Fundraising Ltd
-
£13 ROI
-
£5k budget
-
-
Tractor
-
Sharrocks service booked in.
-
-
Risk assessment update
-
Fencing quote
-
£4k circa - needs approval
-
-
Mike and Ste spoke to Fundraising contact
3rd Feb - 23rd Feb
-
Drainage pipe under car park - seems to have worked for now
-
Need to think about chamber, inspection pit, ancillary drainage etc and build over summer
-
-
Lighting ducts NOT yet installed as of 22.02.20
-
Reunion on Feb 20th has been postponed
-
Mike met the fencing company for a 2nd quote for palisade-style fencing
-
Website ready to go live
-
Bookings form needs tweaking
-
Teams photos to be updated
-
-
Have emailed SAGE
-
Tractor serviced
-
Oil filter needed and is being dropped off (Or could be Air Filter?!)
-
Oils, radiator etc. topped up
-
Small tractor has a cracked engine block and needs selling/scrapping
-
Flail is okay - will need new blades next year
-
-
New small tractor needed
-
Fencing - £8,159.00 - Go ahead from Committee to spend money
24th Feb - 31sr Mar
-
Paid £1,700 to fencing contractor
-
Perimeter ditches now cleared
-
Agreed containers to go on Car Park (these are to be single use)
-
Emailed Peel to tell them about cable
-
Architect picking up with Peel - as middle lighting is not going to be needed then this is the reason the cabling was not out under the car park
-
Architect suggested that the cabling COULD be run at the back of some fencing and hidden under conduit
-
Team believe that canteenering lights is possible (see above)
-
-
RHS supplies were picked up - great team effort!
-
Launched website
-
Received notification about return to outdoor scouting (groups of 15) by March 29th 2021
-
Expenses for toilet
-
Booking form nearly complete
-
Funding meeting moved to Wednesday 10th March 2021
-
Funding applications continue
-
Submitted Duchy of Lancaster grant application for £2,000 (will be assessed in June)
-
Funder contact suggested a seminar (hosted by him and with input from Mike and Ste) in mid April
-
-
Met Councillors online March 10th
-
Submitted Manchester Guardian Society application
-
Filmed Rotary video submission for £1,000 for new tractor
-
Contacted Fay @ Salford re funding
​
​